Construction Season for SOHI

It is construction season and the SOHI District and surrounding neighborhoods are seeing the effects. Here is a list of sites that DPW will be tackling this summer in a project to replace sewer mains that are over 100 years old. The majority of these sites will take two to three weeks unless noted.

Site #1: 25th & Michigan

Site #2: 27th Street (State to St. Paul) 4 weeks in total

Site #3: Clybourn (26th to 30th)

Site #4: Michigan (24th to 27th)

Site #5: St. Paul (27th to 28th)

Completion date for all projects is August 31st, for a total of 90 days. If you have any questions on this or other work going on in the area, please feel free to give me a call at (414) 933-9007.